Question

​If I am doing a permit that DOTD will approve, can I submit the Final Report or do I have to ​submit each recommended deliverable?

Answer

DOTD recommends that work submitted to DOTD for approval is done according to the Traffic Process and Report.  If a final report is submitted without interim approvals during the process, any parts of the process that aren’t done according to DOTD’s policies will require a revision and resubmittal.

Category

Miscellaneous